What is the purpose of keeping tremie pipe’s tip immersed in freshly-placed concrete for about 1m in underwater concreting?

  What is the purpose of keeping tremie pipe’s tip immersed in freshly-placed concrete for about 1m in underwater concreting? The size of tremie pipe is about 300mm with sections having flange couplings fitted with gasket to prevent water leakage. The tremie pipe should be closed initially to prevent water from entering the pipe. It should be designed with sufficient thickness and weight so that it would not be buoyant when empty inside water. The placement of tremie concrete is commenced by putting the closed pipe underwater to the location for concreting, followed by partial filling of tremie pipe with concrete. In order to have tremie concrete flowed out of the pipe, it is necessary to fill the pipe with concrete of sufficient height to overcome the water pressure and frictional head. After that the tremie pipe is raised about 150mm to allow concrete to flow out. To enhance sufficient bonding, each succeeding layer of concrete should be placed before the preceding layer has reached

HOW DO YOU INSTALL ELECTRICAL CONDUIT ON CONCRETE SLAB???WHAT IS THE SPECIFICATION FOR SLAB CONDUITING???

SLAB CONDUITING

1)   Preparation of slab conduiting drawing by electrical contractor.

2)   Verification by electrical dept. and approval by Engg dept authorized signatory.

3)   Slab conduiting on site as per approved plan.

Accessories for Slab Conduiting

1)   PVC Pipes.

2)   Junction Boxes (1 Way to 4 Ways)

3)   Fan Junction Box

4)   Couplers

5)   Reducers

6)   Bends

7)   PVC Cement Solvent

8)   Paint

STANDARD SPECIFICATION FOR SLAB CONDUITING

1)  Conduiting should be done only after slab re-bars are laid and after fixing of PVC cover.

2)  Gap between adjacent conduits should be min. 25mm.

3)  Conduits should not pass through RCC Column.

4)  Conduit drops should be on wall face only.

5)  Conduits should not be in cover zone of re-bars.

6)  Light / Fan points should be painted for easy identification on slab surface soffit (slab shuttering).

7)  Conduits & Junction openings to be sealed to avoid choking and should be touching shuttering.

8)  Light / Fan / TV / Tel. / Bracket light points should be as per approved electrical layout drawing of slab.

Case Study 1:

In no case; electrical conduits shall be placed in the cover zone. For that, if required, either wall is to be shifted if it is 4” or provide 5” wall as the case may be. The same shall be confirmed by the Site In-charge with respective Project In-charge.



Case Study 2 :

The electrical junction boxes should be clearly touching the shuttering at soffit of slabs and there should not be any gap in between. If the above procedure is not followed; then after deshuttering one has to chip concrete to expose electrical points which is not at all allowed. Hence all are requested to follow below given precautions/ solutions on site to avoid such problems. This will result in breaking of junction boxes while the labours are walking on top of slab.

1- Use additional PVC ring piece in the bottom of the electric box so that elect. boxes are
touching shuttering which is lifted up due to slab reinforcement.
2- As far as possible, lay electrical conduits on main reinforcement instead of distribution
reinforcement so that lifting of conduits is avoided.
3- Make sure that elect. boxes are properly tied with reinforcement so that at the time
of concreting, they are not lifted up due to pressure.

• This is applied only when we are not using deep junction boxes (we are always using deep junction boxes)









Comments

Popular posts from this blog

What Is GGBS ?? What is the advantage of using GGBS as replacement of cement in concrete??What Is The Differences Between GGBS and PFA

DOOR FRAME // POINTS TO BE CONSIDERED AND CARE TO BE TAKEN WHILE ERECTING THE DOOR FRAME//HOW TO CALCULATE DOOR FRAME HEIGHT

What is the difference between carbonation and carbon dioxide attack?