PILING WORK IN DETAIL
- Get link
- X
- Other Apps
PILING
1. Type Of Piles To Be Deployed
This would depend upon the site conditions. For a particular project, piles may be pre-cast or cast-in-situ depending upon the site requirements. Geotechnical investigations are carried out to find soil strata before start of any piling work.
2. Setting out for Piling Works
Bench mark and reference axes shall be furnished for the work and positions of piles accurately located as per drawings.
3. Materials For Casting Piles
Cement, water, aggregates and reinforcement are the main materials deployed for piling work.
4. Cement
Portland pozzolana cement conforming to IS 1489 with C3A (tri-calcium aluminate) content below 7% shall be used for piling. Concreting should be done to grade M 250 such that cement content will not be less than that mentioned in specifications. Water-cement ratio, including water-content in aggregates, shall be limited to 0.50. The slump of concrete shall be 125 to 175 mm in order that concrete can be placed/dropped into place properly.
5. Water
Water used for concrete work shall be clean and free from deleterious acids, alkalis or organic materials.
6. Aggregates
Maximum size of coarse aggregate used for piling shall be 20mm.
7.
Reinforcement
All reinforcement used in piling works shall be of tested steel. The same shall be fabricated and put in place as per drawings. Longitudinal main reinforcement bars shall be of complete lengths and, where this is not possible, separate lengths shall be spliced or butt welded.
8. Cube Tests of Concrete used for Casting Pile
Six cubes shall be drawn for each day’s concreting and/or for every 25 piles cast for 7-day and 28-day compressive strength tests.
9. Pile shoes
for precast piles
Driven piles are provided with either flat or conical cast iron shoes at the bottom for protecting the top of the pile during driving in hard ground. The area of the top of the shoes shall be such that the stress in the concrete in this part of the pile is within the safe limits.
10. Checklist for Casting and Driving of pre-cast piles
ENGG / FR / 08 |
|
|||||
Work-site: |
||||||
Check List For
Casting & Driving Of Pre-Cast
Piles Report No: Dated: |
||||||
Sr No |
Parameter |
Observation |
||||
1 |
Job
for which piles
are required |
|
||||
2 |
Drawing
number |
|
||||
3 |
Pile group number |
|
||||
4 |
Pile
number |
|
||||
5 |
Pile
capacity in tonnes |
|
||||
6 |
Length
of pile in meters |
|
||||
7 |
Check formwork of pile |
|
||||
8 |
Check reinforcement of pile |
|
||||
9 |
Check concrete mix |
|
||||
10 |
Check maximum size of aggregate |
|
||||
11 |
Check brand and type of cement |
|
||||
12 |
Check number of concrete test cubes taken |
|
||||
13 |
Check curing period required |
|
||||
14 |
Safe date of lifting the pile |
|
||||
15 |
Whether
vertical or raker
type of pile |
|
||||
16 |
Actual
rake in mm |
|
||||
17 |
Pile diameter
in mm |
|
||||
18 |
Pile
length in meters |
|
||||
19 |
Mark
and check center-line of bore |
|
||||
20 |
Cut-off
elevation at pile top |
|
||||
21 |
Ground
elevation |
|
||||
22 |
Time of starting
boring |
|
||||
23 |
Time of completing boring |
|
||||
24 |
Method
of boring |
|
||||
25 |
Length, in
meters, of casting if used |
|
||||
26 |
Length of
boring in soil, in
meters |
|
||||
26 |
Length of
boring in founding
stratum of rock, in
meters |
|
||||
28 |
Depth
at commencement of chiseling, in meters |
|
||||
29 |
Type of
chisel deployed |
|
||||
30 |
Weight
of chisel deployed, in Kgm |
|
||||
31 |
Drop
of chisel, in meters |
|
||||
32 |
Number
of blows of
chisel |
|
||||
33 |
Elevation
at start of
chiseling |
|
||||
34 |
Elevation
at completion of
chiseling |
|
||||
35 |
Penetration
in metres |
|
||||
36 |
Strata at
pile bottom |
|
||||
37 |
Check
and confirm pile lowering and centering in position in position |
|
||||
38 |
Check
grouting mix |
|
||||
39 |
Check
suitability of sand |
|
||||
40 |
Check
water-cement ratio |
|
||||
41 |
Check and
note grout pressure in
Kg/ sq.cm. |
|
||||
42 |
Time
of starting grouting |
|
||||
43 |
Time
of completing grouting |
|
||||
44 |
Grout
consumption in cum |
|
||||
45 |
Check
deviation, in mm, in
pile alignment and
positioning after grouting. |
|
||||
46 |
Check
whether pile has
been cut-off at
the correct level |
|
||||
47 |
Length
of pile to be
built-up, in meters |
|
||||
Other
comments |
|
|
||||
Contractor’s
Engineer: |
Site Engineer: |
|
||||
11. Checklist For
Bored Cast-In-Situ Piles
ENGG / FR / 09 |
T |
|
|||||
Work-site: |
|
||||||
Check List
For Bored Cast-In-Situ Piles Report No. Dated: |
|
||||||
Sr No |
Parameter |
Observation |
|||||
1 |
Job for
which piles are
required |
|
|||||
2 |
Area / Location |
|
|||||
3 |
Drawing number |
|
|||||
4 |
Pile group number |
|
|||||
5 |
Pile number |
|
|||||
6 |
Pile capacity
in tonnes |
|
|||||
7 |
Total number of
piles in the group |
|
|||||
8 |
Number of piles
cast in the group |
|
|||||
9 |
Whether vertical
or raker type
of pile |
|
|||||
10 |
Actual rake
in mm |
|
|||||
11 |
Pile
diameter in mm |
|
|||||
12 |
Pile length
in meters |
|
|||||
13 |
Mark and
check center-line of
bore |
|
|||||
14 |
Bore diameter
in mm |
|
|||||
15 |
Method of
boring |
|
|||||
16 |
Bore length
in soil, in meters |
|
|||||
17 |
Bore length
in founding stratum, in
metres |
|
|||||
18 |
Depth at
commencement of chiseling, in meters |
|
|||||
19 |
Type of
chisel deployed |
|
|||||
20 |
Weight of
chisel deployed, in Kgm |
|
|||||
21 |
Drop of
chisel, in meters |
|
|||||
22 |
Rate of
chiseling |
|
|||||
23 |
Number of blows |
|
|||||
24 |
Elevation at
commencement of chiseling |
|
|||||
25 |
Elevation at
end of chiseling |
|
|||||
26 |
Penetration,
in meters |
|
|||||
26 |
Elevation at
pile bottom |
|
|||||
28 |
Elevation at
pile cut-off |
|
|||||
29 |
Elevation at
ground level |
|
|||||
30 |
Strata at
pile tip |
|
|||||
31 |
Check details
of reinforcement cage |
|
|||||
32 |
Check placement
and centering of
reinforcement cage |
|
|||||
33 |
Check brand
type of cement
used |
|
|||||
34 |
Check maximum
size of aggregate |
|
|||||
35 |
Check mix
of concrete |
|
|||||
36 |
Check water-cement ratio |
|
|||||
37 |
Length of pile
concreted, in meters |
|
|||||
38 |
Number of
concrete test cubes
taken |
|
|||||
39 |
Check marking
of concrete test
cubes |
|
|||||
40 |
Method of
concreting of pile |
|
|||||
41 |
Volume of
pile concreted, in cum. |
|
|||||
Other comments |
|
|
|||||
Contractor’s Engineer: |
Site Engineer: |
|
|||||