What is the purpose of keeping tremie pipe’s tip immersed in freshly-placed concrete for about 1m in underwater concreting?

  What is the purpose of keeping tremie pipe’s tip immersed in freshly-placed concrete for about 1m in underwater concreting? The size of tremie pipe is about 300mm with sections having flange couplings fitted with gasket to prevent water leakage. The tremie pipe should be closed initially to prevent water from entering the pipe. It should be designed with sufficient thickness and weight so that it would not be buoyant when empty inside water. The placement of tremie concrete is commenced by putting the closed pipe underwater to the location for concreting, followed by partial filling of tremie pipe with concrete. In order to have tremie concrete flowed out of the pipe, it is necessary to fill the pipe with concrete of sufficient height to overcome the water pressure and frictional head. After that the tremie pipe is raised about 150mm to allow concrete to flow out. To enhance sufficient bonding, each succeeding layer of concrete should be placed before the preceding layer has reached

SPECIFICATION FOR READY MIX CONCRETE SUPPLY (RMC)..WHAT IS THE REASONS BEHIND THE COLLAPSE SLUMP OF CONCRETE??

 SPECIFICATION FOR READY MIX CONCRETE SUPPLY (RMC)

 

A) Technical Specifications.

   Concrete Mix designs of all grades to be used along with past cube results/ trial results shall be approved. Any change in CMD subsequently shall also be approved.

   Max. cement content shall not exceed 450 Kg/Cum. And W/B ratio shall not be less than 0.32. Use of Fly ash is must for all grades of concrete.

   No Mahad Sand, Crusher waste product, stone dust to be used. Only Vaitarna sand or Crushed sand to be used.

   Cement slurry in starting will be brought by RMC supplier. Cement slurry shall not be pumped into pouring place since w/c ratio is higher than required.

Acceptance criteria for concrete at the time of arrival on site.

    Max. slump permitted at the time of arrival = 125mm. No collapse slump will be accepted. Slump at Plant will be 150mm. to 160mm. Slump Cone and Cube Moulds must be kept at Batching Plant also, for checking concrete. No addition of water and super plasticizer is allowed in transit mixers unless prior permission is taken from the company engineer in charge.

     Max. Temperature permitted at the time of arrival = 34 degree centigrade. Temperature shall be controlled by using ice water. Transit Mixers and Pipes, to have Hessian Cloth wrapped around same and to keep it wet.

Casting of concrete cubes.

Cubes will be cast by Lab Technician at Site. As well as RMC Lab. Tech. from the same batch of concrete. It has been observed that even though Site lab technician and RMC person are casting cubes from same batch, variation is found in cube results. Some time our cubes passes and RMC cube fails, and vice a versa. Hence following points shall be followed to minimize chances of variation/ error in cube results.

1) Cubes shall be kept in site curing tank instead of taking them to RMC plant.

2) Cube testing of both will be tested on site lab. In presence of site engineer and RMC representative.

3) Min. 13 cubes shall be cast. 3 Companion Cubes will be taken 3 times + 4 Cubes for 28 days testing.

 Acceptance criteria for compressive strength of cubes.

Cubes cast on site & cubes cast by RMC will be tested on site lab in presence of site Engineer & representative of RMC, & if any one of them passes, then it will be considered acceptable & no penalty, to be put. If we do not get the required compressive strength of concrete, we will impose a penalty on RMC supplier, which will go on doubling, if the cube results continue to fail.

Compressive strength (Kg /sq.cm) requirement is as follows.

Grade of Concrete

    5 days strength

   15 days strength

    28 days strength

Min. Cube to be tested

3 nos

   3 nos.

 4 nos.

M30

   248

   248

 330

M35

   285

   285

 380

M40

   322

   322

 430


B)    Schedule and intimation of concrete supply.

Concreting can be supplied on intimation within 24 hrs. Tentative Schedule for 1 week will be given by site in advance. Concreting will start at 8.00 a.m. & should get over by 9.00 p.m.

 C)    General terms and conditions.

 1)    Labour - 6 Nos. for shifting Pipes, ghodas etc. also will have to be supplied by RMC supplier.

 2)    RMC supplier to ensure that concrete Pump should not fail. If concrete pump fails, there will be heavy penalty on RMC supplier.

 3)    Pipes, including bending radius pipes also to be sent for Pouring concrete on slab. Proper arrangements for supporting pipes shall be made by RMC in such a way that they do not disturb shuttering of slab.

 4)   Supervisor - 2 Nos. to be available at Concrete Pouring Point and communication with Plant and pouring plant with Mobile

 5)   There should be no interruption in concreting supply, for slab. Minimum pour - 50cum Maximum pour - 300cum.

 6)   RMC supplier shall submit Concrete Mix Design of concrete mix, at the time of every pour.

 7)   Washing and cleaning of transit mixers shall be done by RMC supplier, in such a way that sites cleanliness is not affected.

 8)   All transit mixers must have cleaner.

 9)   All basic safety norms like wearing helmet etc shall be observed by RMC personels, supervisors and labours etc.

 10)  During rains, mouth of transit mixer shall be covered to prevent rain water from getting inside transit mixer.

 11)   If due to any delay from the RMC side, if concrete is not pumped for more than 3 hrs. after arrival on site, then same will be rejected.

Some guidelines for slump adjustment and to avoid pump choke up.

 Basically the collapse slump can be avoided if the following points listed below are taken care :

1.  Number of times RMC concrete pumping is stopped, due to various reasons at site, including changing of direction in pipes supplying concrete on top of slab being concreted. If pump is stopped for any reasons, keep the pump working, sucking backwards i.e. 2 strokes back and 1 stroke forward, again wait for 1 or 2 min. and if pumping does not start, again repeat the same & so forth up to regular pumping starts. Cycle - Suck 2 push 1, suck 2 push 1, suck 2 push 2, up to the RMC concrete pumping restarts.

2.  A operator observing at the Pump hopper level should ensure that concrete level does not go below, the blade level so that air is not sucked or place a mirror in position, so that operator can see the level of concrete in hopper & ensure that concrete in hopper does not go below the blade level.

3).   Slump for pumping should be 125mm.

4).   Concrete will be sent on site, with a slump of less than 125mm and if required, to adjust for making it pumpable, we will add (1:4) super plasticizer: water, at site itself, thereby ensuring that case of collapse slump of RMC concrete does not occur at all.

4.   The temperature of 34-degree centigrade will be allowed, for the concrete supplied at site, when the transit mixer actually arrives & not at placing the concrete, since there can be delays at placing point due, to site conditions.

6.   Wetted Hessian cloth, to be placed on RMC concrete supply pipes & transit mixer, in order to control the temperature of concrete.

Reasons for additional water in concrete, which makes the concrete with Collapse Slump is:

a)   There can be fault with valve supplying water in the drum of transit mixer, for cleaning the transit mixer drum, after concreting is completed .

b)   After every supply of concrete, the mixer drum is washed. This water may not be removed and fresh concrete is loaded in the transit mixer, at the RMC plant.

Hence during mixing of concrete in pan mixer at the RMC plant, in the first 2 mixes of 0.5 cu.m, the operator to see the workability of concrete. If required, then in the balance 10 batches of 0.5 m3, water to be added in lesser quantities. (Assuming one batch of concrete is 0.5 cu.m)

Hope the above process, will solve the problems of collapse slump & we can work in more harmonious manner, achieving Quality, Speed & Economy.

Comments

Popular posts from this blog

HOW DO YOU INSTALL ELECTRICAL CONDUIT ON CONCRETE SLAB???WHAT IS THE SPECIFICATION FOR SLAB CONDUITING???

What is the purpose of keeping tremie pipe’s tip immersed in freshly-placed concrete for about 1m in underwater concreting?

What Is GGBS ?? What is the advantage of using GGBS as replacement of cement in concrete??What Is The Differences Between GGBS and PFA